In 1999, voters in San Francisco approved a $299
million bond measure to provide partial funding for a skilled nursing
facility. The estimated project cost was $401 million, and the budget
included 3.8 percent per year in anticipated cost escalation. In early
2005, initial bids revealed a projected budget shortfall of $96
million.
A May 2005 state controller’s report notes that the
overrun was attributed to cost escalation and that, while 3.8 percent
per year was budgeted, actual cost escalation for the 23 months prior
to May 2005 was 2.4 percent per month. The controller’s report goes on
to forecast probable project costs at $600 million to $640 million, a
50 percent increase in forecasted costs.
What is cost escalation?
Simply put, cost escalation is the continual change in
construction labor and material costs. And as the example above
illustrates, cost escalation must be planned in every major health
care project. While the San Francisco case is an extreme example, even
“normal” escalation can and will result in millions of dollars in
project costs that a facilities professional must account for when
planning a project budget.
Recently, the national average construction escalation
has been higher than historical escalation values. The reasons for
this are varied. Oil prices have tripled in the last five years, and
the price of gas has doubled in the same time. Everything on a
construction site, including workers, is brought in a gas-burning
vehicle. Common building products such as polyvinyl chloride (PVC) and
asphalt include petroleum in their manufacturing processes. It is not
an overstatement to say that the price of oil is impacting virtually
every construction site in America.
Additionally, the global market and rapid growth in
places like China have fueled supply and demand impacts on commodities
like copper and scrap metal, which continue to increase in value. One
major contractor reports that the cost of copper wire increased by 167
percent between 2004 and the end of 2007. The cost of ceiling tiles
doubled in the same time frame, and the cost of structural steel
increased by 68 percent. In some markets, labor is also a scarce
commodity, and the competition for qualified and experienced health
care contractors can be very intense, also driving up costs.
State and federal regulations are also contributing to
the increasing cost of health care projects. California’s 1994 seismic
legislation has resulted in the need for billions to be spent on
upgrading health care facilities. With each project competing for
limited construction materials and labor, the cost of hospital
construction in California has skyrocketed at double-digit annual
rates to costs approaching $700 per square foot.
Factors to consider
So what is a prudent health facilities manager
to do when building a project budget model? Following are some factors
they must keep in mind:
Construction market
dynamics. Global, national and local markets are all dynamic,
but they do not all move in lockstep. National publications are
helpful, but they typically only address national issues.
Understanding the issues and trends in a specific geographic area and
how they impact health care construction is the first step in making
reasonable projections about how escalation will impact a project.
Experienced health care contractors keep close track of the material
and labor markets in their business areas, and they are the best
source of up-to-date cost information and local trends.
In the early budget modeling phase of a project,
facilities professionals should seek out multiple contractors and ask
them to share what they are seeing in current costs and where they see
those costs heading. When that is coupled with information in national
publications, facilities professionals will have a reasonable basis
for deciding how to account for current market dynamics. Simply
carrying 3 percent because it is a historical average is a recipe for
trouble.
Equipment, furnishings
and finishes costs. Every line item in a construction budget
needs to be evaluated with respect to potential annual cost increases.
Medical equipment, furniture, signage, kitchen equipment and other
similar items are all examples of project budget line items that are
each subject to yearly escalation.
Most hospitals routinely work with furniture and
equipment vendors, and these are excellent sources of information on
cost trends for their products. Professional equipment or furniture
planning consultants can also provide valuable information on
projected costs. For each project line item there is a specialist with
whom a health facilities professional can consult regarding future
cost projections. It is worth the time to talk to as many people as
possible to get a variety of opinions before settling on escalation
projections.
Design and consultant
costs. These costs are also subject to increases, primarily due
to annual salary raises. If facilities professionals are in the early
modeling stage and don’t yet have contracts in place, they can usually
account for these costs on a percentage basis. For example, if it is
assumed that design/consulting costs will range between 10 percent and
15 percent of a construction cost, then as long as the escalation is
factored into the construction costs, it will automatically be
accounted for in the consultant costs. A normal annual consultant
salary increase will probably be in the 3 percent to 5 percent range,
but that information is only helpful if the salaries are known up
front. Consultant cost escalation is not typically a major concern
when building a health care project budget.
Cost compounding.
A common rule of thumb for calculating the construction cost
escalation is to estimate the number of years until the midpoint of
the construction schedule and then compound the annual escalation rate
to that midpoint.
The closer a facilities professional gets to the
actual bid time of a project, the less impact that escalation is
likely to have on the project. For example, if a facility is three
years away from the midpoint of construction and the facilities
professional determines that 5 percent is the appropriate rate, he or
she should compound 5 percent for three years and include that dollar
value in the budget for escalation.
If the facilities professional is three months away
from bidding the project, the current costs are probably a reasonable
indicator of what the costs will be on bid day, and the facilities
professional might be able to reduce the escalation projections.
Mitigating escalation impacts
Beyond simply projecting future costs and hoping
for the best, there are specific strategies that a facilities
professional can implement in an attempt to mitigate escalation
impacts on the project. They include the following:
Build the team early.
Building a health care project team early is a good idea for a number
of reasons, and escalation mitigation is one of them. Assembling an
experienced design team, construction team and program management team
early on allows facilities professionals to tap into the experience
and resources of many firms.
Health care builders and consultants typically keep
good track of their project costs in detail and thus have a
significant database from which to draw assistance in developing a
budget model. Beyond that, having the entire team assembled early
allows facilities professionals the clear opportunity to begin
building early. Typically, the earlier ground is broken, the earlier
costs are locked in and the impacts of spiraling escalation are
controlled.
Retain major
subcontractors early. If the primary project team is on board
early, they can also provide advice on the merits of bringing on key
subcontractors early in the process.
This strategy is particularly important when a local
market is busy and work is plentiful. All things being equal, many key
contractors such as mechanical, electrical and plumbing contractors
would prefer to work on non-health-care projects because they are
shorter and less complex. Health care projects are often viewed as
risky by the contracting community.
Thus, in busy markets, health facilities professionals
may want to bring in key subcontractors early in the project to avoid
the prospect of going out to bid and not getting enough bidders to
ensure competitive pricing.
Get early packages
(fast-track construction). More and more, fast-track
construction is becoming the norm for health care projects. The
pressure of increasing costs coupled with the organizational pressure
to finish early and reap the rewards of a new facility is driving
facilities professionals to ask their project teams to issue early
design and construction packages.
These packages consist of design documents that are
issued in advance of the total design being complete. A design team
might issue early site-work and building-foundation packages to allow
a contractor to begin site and foundation work while the design team
finishes the rest of the plans. The benefit of this approach is fairly
obvious in that it allows the facilities professional to turn the
design and construction process into parallel activities instead of a
series of linear ones.
Purchase materials early.
Another benefit to building a broad team early is that it allows
facilities professionals the opportunity to purchase materials early
and lock in pricing earlier.
A contractor or supplier who is in need of a project
might be willing to negotiate and lock in pricing, in exchange for
gaining the business. Again, the project’s construction manager is the
best adviser on these types of issues.
The risk with this approach is always that the price
of the items purchased early will actually decrease or will not
increase as much as was assumed. Typically, once a price is locked in,
any savings or overruns revert to the contractor supplying the
material.
Form effective team
structure and decision-making process. The bottom line is that
“time is money.” The longer it takes to make decisions, the longer it
takes to implement those decisions. Health care projects require a key
management committee that regularly devotes time to the project so the
facilities professional can present key issues, and decisions can be
made quickly.
Undertake contingency
planning. Overall budget contingency planning should attempt to
account for all of the issues that may financially impact a project.
Escalation is only one of those issues, and a facilities professional
cannot overload the contingency to account for every market turn.
Having given the issue proper consideration, the
facilities professional will be able to come up with a reasonable
projection to include in the budget. If the facilities professional
budgets for 4 percent escalation in the main portion of the budget, he
or she might account for another percent or 2 in the contingency to
gain a range of escalation scenarios that might be covered.
Developing a sound model
Early project budget models are often educated
guesses. The further along in the process, the more information is
known and the better a budget model will become. This applies to all
aspects of a budget model, including escalation.
There are times when circumstances result in a
situation such as the one that occurred in San Francisco. While such
scenarios do occur and are very difficult to deal with, they are not
the norm.
By implementing the strategies outlined above, health
facilities professionals can develop sound budget models that hold up
to escalation and the myriad other issues faced during the course of a
health care project.