"How to Improve Lab Project Delivery
With Early Contractor Involvement", (c) Ramin Cherafat, Laboratory
Design, 10/07
As
biotechnology, nanotechnology, and a host of other “technologies” have
exploded, so has the need for industrial, research, and academic
laboratories. The traditional methods of delivering laboratory
facilities—design by an architect, receiving bids, and constructing the
facility—have been stretched. Industries such as pharmaceuticals require
new labs to be brought on line in months. Due to the nature of their
grant funding, even laboratories in the public sector need to be
designed and constructed in shorter time frames than ever before. In
general, the design/bid/build approach won’t accommodate this rapid a
schedule. A different model is required.
A growing number of institutions and companies are examining a different
approach to designing and building lab facilities. That approach is
highlighted by bringing the construction professionals—the general
contractor or construction manager—into the project much earlier than
the bid phase. A growing number of owners are recognizing that the
construction team should be in place simultaneously with the architect’s
design team. This is a departure from standard project delivery and
requires the traditional “triumvirate” of owner, architect, and
contractor to work together in new, more collaborative ways.
The benefits, however, of involving the construction entity at a
laboratory’s project inception are well worth the effort. Those benefits
extend to better management of the project budget and project schedule,
and increased quality of the finished facility.
Budget Nearly every laboratory project is “designed to
a budget” instead of “budgeted to a design.” In a traditionally
delivered project, owners are apt to receive bids for construction that
are in the range of 10 to 20% over budget. This necessitates that the
owner adjust his budget upward (never a popular move) or that the
architect must make design changes to find the savings (also an
unpleasant task, which can result in additional design costs and
schedule delays).
An experienced laboratory contractor can help evaluate project costs,
particularly if the firm is part of the design process from the
beginning.
SAFC Biosciences, a division of Sigma-Aldrich, worked closely with their
construction manager, McCown Gordon of Kansas City, Mo., before
constructing a new 28,000-ft2 facility in Lenexa, Kan. When the
construction manager learned that SAFC was likely to outgrow the
proposed 28,000 ft2 facility and require another 12,000 ft2 within two
years, the team proposed a construction approach that provided
significant longer term value to the owner. That approach was to
construct the shell of both facilities (a combined 40,000 ft2), fully
completing only the initial 28,000. By doing so, items like steel and
roofing systems could be ordered and constructed with one mobilization.
The savings realized compared with completing the two sections
separately was $500,000.
In addition, expansion considerations were made for both the mechanical
and electrical infrastructure during phase one at a fraction of what
those costs would have been to retrofit and/or replace the systems in
the future.
Schedule The design/construction schedule is always
critical on a laboratory project. By having the architect and contractor
working together from the beginning, many tasks can be overlapped;
that’s the essence of fast-track scheduling. Because the contractor is
engaged during the design process, early cost information can be
developed while there is still time to make design changes.
Additionally, materials and equipment with long lead times can be
ordered by the contractor, further accelerating the schedule.
Extremely precise scheduling allowed Sanofi-Aventis to maintain full
production of Allegra at that company’s renovation of a 90,000-ft2
facility in Kansas City. By carefully phasing the project in seven
phases, temporarily relocating key equipment and mechanical systems, and
working round the clock, McCown Gordon was able to complete the
renovation on time with no impact to production. The cost savings were
inestimable.
Quality As long-term investments, laboratories must address
quality issues both during design and construction. That quality begins
in the design phase and continues throughout construction. When designer
and contractor work together with the owner to define the factors that
impact the lab’s quality criteria, the final result is much more likely
to achieve those criteria.
Mechanical/electrical/plumbing systems are critical to the laboratory’s
operation. The first indication of whether MEP systems meet quality
criteria occurs well before the actual process of commissioning of those
systems. It starts with effective pre-planning and coordination between
contractors and designers. Design and construction must mesh perfectly
here or problems will be detected during commissioning. Correcting
design or construction problems at the commissioning stage is costly and
will impact the schedule. Well-designed MEP systems and the
well-executed construction of those systems requires designers and
construction managers to work more closely together from the start.
The quality of a completed laboratory project is directly related to the
qualifications of both architect and contractor. In traditional project
delivery, the contractor is only brought on board after a lengthy
bidding phase, and the successful bidder’s qualifications and experience
in constructing laboratory facilities play only a minor role. By
selecting a contractor at the project’s inception, the owner can help
ensure that the final constructed project has a much greater chance to
meet all the quality criteria. Selecting the contractor (or construction
manager) based upon qualifications will normally require some creativity
on the owner’s part. Qualifications-based selection, long used for
selecting architects, is appropriate. A design/build approach may also
be advantageous.
Subcontractors Contractors of lab projects typically
subcontract 75 to 85% of the construction work. This crucial fact means
that owners must insist that their contractor rigorously examine the
available pool of subcontractors and select subs that understand
laboratory construction. It’s not enough to simply say it’s the
contractor’s problem to find subs; owners should be invested in the
process as well.
In summary, owners of laboratory facilities can increase their chances
of a successful project by engaging a contractor or construction manager
simultaneously with their architect. The combined synergy of a designer
and builder who understand the unique nature of laboratories can
preserve the owner’s budget, maintain the project schedule, and ensure
that quality criteria are met. That’s the advantage of an early start.
|
|